Tenaga Kerja
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Pekerja | OH | 0,4600 | Rp 126.500,00 | Rp 58.190,00 |
| 2 | Tukang Batu | OH | 0,1150 | Rp 145.000,00 | Rp 16.675,00 |
| 3 | Kepala Tukang | OH | 0,0115 | Rp 155.000,00 | Rp 1.782,50 |
| 4 | Mandor | OH | 0,0460 | Rp 172.500,00 | Rp 7.935,00 |
| Subtotal Tenaga Kerja | Rp 84.582,50 | ||||
Bahan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Beton Ready Mixed fc 25 MPa | m³ | 1,0200 | — | — |
| 2 | Kayu Kaso 5/7 Kelas II | m³ | 0,0324 | — | — |
| 3 | Multiplek 12 mm | lbr | 0,2546 | — | — |
| 4 | Paku 7 cm | kg | 0,1486 | Rp 48.485,00 | Rp 7.204,87 |
| 5 | Joint Sealant | kg | 0,6250 | — | — |
| 6 | Curing compound | L | 1,3333 | — | — |
| 7 | Polythene 125 mikron | kg | 0,5556 | — | — |
| Subtotal Bahan | Rp 7.204,87 | ||||
Peralatan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Vibrator Beton/ Concrete vibrator [1] | hari | 0,0861 | — | — |
| 2 | Concrete cutter | hari | 0,0068 | — | — |
| Subtotal Peralatan | Rp 0,00 | ||||
[1] HSD alat sudah termasuk operator alatnya (tanpa pembantu operator)
Rekapitulasi Harga
Overhead dan profit pada halaman analisa menggunakan persentase standar 7% dan 8%. Persentase dapat diubah di halaman Kalkulator.
Sumber Dokumen
Direktorat Jenderal Bina Konstruksi · 47/SE/Dk/2026