Tenaga Kerja
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Pekerja | OH | 1,2300 | Rp 126.500,00 | Rp 155.595,00 |
| 2 | Tukang Batu | OH | 0,2875 | Rp 145.000,00 | Rp 41.687,50 |
| 3 | Kepala Tukang | OH | 0,0288 | Rp 155.000,00 | Rp 4.464,00 |
| 4 | Mandor | OH | 0,1230 | Rp 172.500,00 | Rp 21.217,50 |
| Subtotal Tenaga Kerja | Rp 222.964,00 | ||||
Bahan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Semen Portland (PC) | kg | 383,0000 | Rp 1.119,00 | Rp 428.577,00 |
| 2 | Pasir Beton | kg | 764,0000 | Rp 224,00 | Rp 171.136,00 |
| 3 | Agregat Kasar | kg | 934,0000 | Rp 394,00 | Rp 367.996,00 |
| 4 | Air | L | 195,0000 | — | — |
| 5 | Kayu Kaso 5/7 Kelas II | m³ | 0,0324 | — | — |
| 6 | Multiplek 12 mm | lbr | 0,2546 | — | — |
| 7 | Paku 7 cm | kg | 0,1486 | Rp 48.485,00 | Rp 7.204,87 |
| 8 | Joint Sealant | kg | 0,6250 | — | — |
| 9 | Curing compound | L | 1,3333 | — | — |
| 10 | Polythene 125 mikron | kg | 0,5556 | — | — |
| 11 | Zat aditif beton (concrete admixture) | kg | 1,2000 | — | — |
| Subtotal Bahan | Rp 974.913,87 | ||||
Peralatan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Molen/Beton Mixer 0,35 m³ + feeder Bahan [1] | hari | 0,1475 | — | — |
| 2 | Tandon Air kap. 2 m3 | hari | 0,7568 | — | — |
| 3 | Vibrator Beton/ Concrete vibrator | hari | 0,0861 | — | — |
| 4 | Concrete cutter | hari | 0,0068 | — | — |
| Subtotal Peralatan | Rp 0,00 | ||||
[1] HSD alat sudah termasuk operator alatnya (tanpa pembantu operator)
Rekapitulasi Harga
Overhead dan profit pada halaman analisa menggunakan persentase standar 7% dan 8%. Persentase dapat diubah di halaman Kalkulator.
Sumber Dokumen
Direktorat Jenderal Bina Konstruksi · 47/SE/Dk/2026