Tenaga Kerja
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Pekerja | OH | 0,4800 | Rp 126.500,00 | Rp 60.720,00 |
| 2 | Tukang Batu | OH | 0,1200 | Rp 145.000,00 | Rp 17.400,00 |
| 3 | Kepala Tukang | OH | 0,0120 | Rp 155.000,00 | Rp 1.860,00 |
| 4 | Mandor | OH | 0,0480 | Rp 172.500,00 | Rp 8.280,00 |
| Subtotal Tenaga Kerja | Rp 88.260,00 | ||||
Bahan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Beton Ready Mixed fc 30 MPa | m³ | 1,0200 | — | — |
| 2 | Kayu Kaso 5/7 Kelas II | m³ | 0,0252 | — | — |
| 3 | Multiplek 12 mm | lbr | 0,2546 | — | — |
| 4 | Paku 7 cm | kg | 0,1159 | Rp 48.485,00 | Rp 5.619,41 |
| 5 | Joint Sealant | kg | 0,6250 | — | — |
| 6 | Curing compound | L | 1,0000 | — | — |
| 7 | Polythene 125 mikron | kg | 0,4167 | — | — |
| 8 | Dowel diameter 25 mm (BjTP) | kg | 38,7836 | Rp 15.602,00 | Rp 605.101,73 |
| 9 | Tie bar diameter 16 mm (BjTS) | kg | 6,6290 | Rp 15.602,00 | Rp 103.425,66 |
| Subtotal Bahan | Rp 714.146,80 | ||||
Peralatan
| No | Produk | Satuan | Koefisien | Harga | Jumlah |
|---|---|---|---|---|---|
| 1 | Vibrator Beton/ Concrete vibrator [1] | hari | 0,0861 | — | — |
| 2 | Concrete cutter | hari | 0,0072 | — | — |
| Subtotal Peralatan | Rp 0,00 | ||||
[1] HSD alat sudah termasuk operator alatnya (tanpa pembantu operator)
Rekapitulasi Harga
Overhead dan profit pada halaman analisa menggunakan persentase standar 7% dan 8%. Persentase dapat diubah di halaman Kalkulator.
Sumber Dokumen
Direktorat Jenderal Bina Konstruksi · 47/SE/Dk/2026